Category: CAPM & PMP

CAPM & PMP Practice Questions – Set 2

1. Reserve Analysis a technique not used in: A. Estimate Costs B. Estimating Activity Duration C. Control Costs D. Determine Budget Answer: C Explanation: Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs. 2. A Project

CAPM & PMP Practice Questions – Set 1

Hi Guys, I am starting posting CAPM & PMP Practice Questions with answers and some of them will have explanation as well. This Series will have 125+ sets. Each set consists of 25 Questions. Hope you will Enjoy the Series. 1. The inputs of the Performance Reporting process include all of the following except for
SiteLock