CAPM & PMP Practice Questions – Set 3
1. What are the performance measurements for the Schedule Control process? A. SV (EV – PV) and SPI (EV ÷ PV) B. SV (PV – EV) and SPI (PV ÷ EV) C. SV (EV – BAC) and SPI (EV ÷…
Connecting Developers to Architectural Excellence
Connecting Developers to Architectural Excellence
1. What are the performance measurements for the Schedule Control process? A. SV (EV – PV) and SPI (EV ÷ PV) B. SV (PV – EV) and SPI (PV ÷ EV) C. SV (EV – BAC) and SPI (EV ÷…
1. Reserve Analysis a technique not used in: A. Estimate Costs B. Estimating Activity Duration C. Control Costs D. Determine Budget Answer: C Explanation: Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule…
Hi Guys, I am starting posting CAPM & PMP Practice Questions with answers and some of them will have explanation as well. This Series will have 125+ sets. Each set consists of 25 Questions. Hope you will Enjoy the Series.…